When we review a pilot build at NexPCB, we look for two different answers: how many units went straight through, and how many ultimately met the acceptance criteria. First-pass yield answers the first question. Final yield answers the second. When comparable figures diverge, the unit histories show which units needed another step before acceptance. That distinction matters on a wearable build where programming, assembly, or calibration can recover units without resolving the cause of a first valid failure.
First-pass yield is the share of units in the defined reporting cohort that pass a defined operation or process on the first valid attempt without qualifying recovery. For a station measure, count distinct units that pass the station on their first valid attempt and divide by the number of distinct units in the agreed station cohort. For a build-level measure, name the operations in scope and count a unit as straight-through when it completes that route on the first valid attempt at each applicable operation without a qualifying retest, repair, or other recovery under the agreed rules.
Final yield is the share of the defined build cohort that meets the applicable acceptance criteria after permitted recovery and disposition. Keep the denominator visible when you report it. A comparable pair uses the same units, process boundary, and acceptance criteria. A board-level process and a finished-device process do not share that boundary, so a difference between their yield figures does not measure recovery. Put the process boundary in the metric label so the chart shows which operations each figure covers.
| What you want to learn | What to count | What to record beside the result |
|---|---|---|
| How reliably one station passes units on the first valid attempt | Distinct units passing on their first valid attempt divided by distinct units in the agreed station cohort | Station, configuration, valid-attempt rules, and cohort rules |
| How often the planned route produces a straight-through unit | Units passing each applicable operation on the first valid attempt without qualifying recovery divided by distinct units in the agreed route cohort | Operations included, what counts as a departure, and cohort rules |
| How many units ultimately met acceptance | Accepted units divided by distinct units in the stated build cohort | Reworked, scrapped, and pending dispositions as applicable |
Agree on what makes an attempt invalid before you review totals. Log an invalid attempt, such as a run interrupted by lost station communication if it meets the agreed rule, but do not classify it as a product failure. The next valid attempt is the first one used for first-pass reporting if no earlier valid attempt exists. A rerun that clears a valid failure belongs in the unit history even when there was no physical repair. If you erase it by retaining the last result alone, the reported first-pass yield no longer represents the same process.
When both figures use the same units, process boundary, and acceptance criteria, a higher final yield shows that some units reached acceptance without passing straight through. Use each unit’s record to distinguish a valid failure, a retest of an unchanged unit, rework such as an adjustment or repair, and the final acceptance decision. Record the action taken, why it was taken, and what the later result showed. Agree which of those actions your pilot report will track as rework so a later build can be compared on the same basis.
For example, a pilot that sees failures at a sensor calibration station should preserve both the first measurements and the actions that led to later passes. A fixture reseat, a firmware correction, and replacement of a sensor can each lead to a passing result, but point toward different follow-up. If failures cluster by station or program version, investigate the setup or test program before attributing the pattern to the sensor. If they cluster by material lot, check the lot history before changing the calibration process.
Read the amount of effort as well as the number of recovered units. A report can show whether the recovery was a quick, defined retest or a longer intervention that depended on engineering. Compare rework and retest time with the route you plan to operate at the next build. If the recovered units required steps the production instructions do not describe, decide whether those steps need to become controlled work or whether their cause should be removed upstream.
Check that the cohort can be reconciled from starts to dispositions. State which units enter each denominator and how the reporting rules handle units still on hold or without a valid attempt. Show those counts separately and distinguish a provisional result from the final calculation. If two reports handle unresolved units differently, reconcile the cohorts before comparing the figures. State whether the report describes boards, assembled devices, or test events; test events can help explain a defect, but they are not additional units in a yield calculation.
Agree a target and the action it triggers before collecting results. As one example, the published wearable production-readiness checks describe an internal pilot control plan that used 98 percent as its PCBA yield review baseline. Falling below that baseline triggered supplier improvement. It was a trigger for that plan, not a universal release target or necessarily a first-pass yield figure.
The yield review shows how the build performed. Use the PVT sign-off criteria to decide what the documented results and open items support releasing.
Our wearable mass-production readiness checklist also recommends reporting both first-pass and final yield. Pair the two figures with the defect distribution, retest and rework effort, and the context needed to interpret variation. A small pilot can reveal a concentration of failures after a fixture change or within a material lot; it may not establish how often that failure will occur in routine volume production.
A useful report shows the count of units entering the defined process and how those units ended up: passed straight through, accepted after permitted recovery, scrapped, or still open. Show the version of the board or assembly and the test setup alongside that breakdown. When the build included both pre-change and post-change units, separate them so the aggregate does not hide the effect of the change. Then point to the dominant defect or repeated intervention and the next action you need to judge it.
Decide ahead of time what a result would trigger. A recurring supplier-related defect may call for supplier investigation and evidence from a later lot. A pattern confined to one station setup may warrant a fixture or setup review followed by a comparable build. If the problem is missing test history, agree on the recording rule and collect the next set of results before treating one headline figure as reliable. Define the follow-up in the same terms as the problem so you can tell whether it worked.
If final yield recovered but the pilot still depended on repeated adjustment, carry that dependency into your decision about what to change between builds. The later report should let you tell whether more units passed the planned route on the first valid attempt at each applicable operation, whether recovery took less effort, and whether those changes occurred under comparable conditions.
First-pass yield counts units that met the stated criteria on the first valid attempt without qualifying recovery. Final yield counts units accepted after any permitted recovery. When both figures use the same units, process boundary, and acceptance criteria, a higher final yield shows that some units reached acceptance without passing straight through. Check the unit records to distinguish retest, rework, and final acceptance.
No. Count the unit once in the applicable cohort denominator. If the first valid attempt failed, keep that result for first-pass reporting; a later permitted pass may contribute to final yield. If the earlier attempt was invalid, log it separately and use the first valid result for first-pass reporting.
It shows that some units were recovered when both figures use the same cohort and process boundary. Look at the failures and recovery steps before judging whether the planned route can repeat the result without extra intervention.
Use Accelerate Now to start a discussion about your pilot scorecard. Bring the process boundary, the first and final counts, and the records for the units that took a different route. That gives us a place to look for what the next build needs to confirm.